SK Ecoplant in final stages to hive off plant construction division About 60 employees move to SPC established to get construction business license

Translated by Kim So-in 공개 2021-10-29 07:55:54

이 기사는 2021년 10월 29일 07:30 thebell 에 표출된 기사입니다.

SK Ecoplant is wrapping up a process to split off its plant construction business, aiming to launch its new entity in January next year.

SK Ecoplant has requested some of the employees of its plant construction division to submit documents required to move to BLH Engineering, industry sources said on Wednesday.

BLH Engineering is a special purpose company (SPC) established for tentatively named SK Green Energy to receive a construction license. SK Green Energy is a newly created entity by hiving off the plant construction business.

SK Green Energy is not allowed to use the construction business license held by SK Ecoplant after the split-off. For this reason, the company seems to make BHL Engineering obtain the license in advance and start construction business immediately after the launch of the new entity through a merger with the SPC.

It is said that it normally takes 30-40 days to obtain a new construction business license. Given this, SK Ecoplant may plan to complete procedures related to the launch of SK Green Energy in mid-December.

About 60 employees will move to BHL Engineering. They will reportedly leave SK Ecoplant on October 31 and start working at BHL Engineering from November. SK Ecoplant aims to support the launch of SK Green Energy by additionally relocating employees of the plant construction division in the future.

Considering that the employee relocation has begun in earnest, SK Ecoplant has apparently reached an agreement with its employees at the end of September by vowing to provide welfare and compensation. Employee opposition has been considered the biggest hurdle in the spin-off of the plant construction division.

A consortium of South Korea-based IUM Private Equity and Mirae Asset Securities, which was picked as a preferred bidder to acquire a majority of SK Green Energy, is actively raising funds. Some analysts expect the fundraising process and the acquisition deal to be completed in November. In this case, SK Ecoplant will be able to launch SK Green Energy in January 2022 as planned.

SK Ecoplant will hive off the bulk of its plant construction business, excluding some operations such as the construction of semiconductor plants, nuclear power generators and data centers, and sell the business to the consortium of IUM PE and Mirae Asset Securities for about 450 billion won ($384 million). (Reporting by Byungkeun Kam)
< 저작권자 ⓒ 자본시장 미디어 'thebell', 무단 전재, 재배포 및 AI학습 이용 금지 >
주)더벨 주소서울시 종로구 청계천로 41 영풍빌딩 5층, 6층대표/발행인성화용 편집인이진우 등록번호서울아00483
등록년월일2007.12.27 / 제호 : 더벨(thebell) 발행년월일2007.12.30청소년보호관리책임자김용관
문의TEL : 02-724-4100 / FAX : 02-724-4109서비스 문의 및 PC 초기화TEL : 02-724-4102기술 및 장애문의TEL : 02-724-4159

더벨의 모든 기사(콘텐트)는 저작권법의 보호를 받으며, 무단 전재 및 복사와 배포 등을 금지합니다.

copyright ⓒ thebell all rights reserved.